Paradise Lakes, Ajman - Emiartes City Construction Updates May 2013
B2 Tower G + 4P+12th Floor Completed Block work is going on at 6th residential typical floor.
 
B4 Tower G + 4P+15th Floor Completed 16th floor slab ready for concrete. Block work is in progress at 8th typical residential floor.
B5 Tower G+4P+25th Floor + Terrace Floor & Health club completed. (100 % Structure Completed) block work and internal plaster work complete up to health club. wall conduting complete 25th floor. floor conduting 10th floor. wall tiles for kitchen and bathroom complete,from 1st floor to 16th floor and 23rd floor to 25th floor. 17,18,19,20,21,22 are remaing. floor tiles 2nd floor to 8th floor complete. celling spray 1st parking to 16 floor. internal wall paint 1st parking to 7th floor. wet area water proofing1st floor to 9th floor. Marking for Ac.
B6 Tower G+4P+25th Floor + Terrace Floor & Health club Completed. (100 % Structure Completed) block work and internal plaster work complete up to health club.wall conduting complete 25th floor. floor conduting 10th floor. wall tiles for kitchen and bathroom complete,from 1st floor to 16th floor and 23rd floor to 25th floor. 17,18,19,20,21,22 are remaining. floor tiles 2nd floor to 9th floor complete. celling spray 1st parking to 25th floor. external colour plaster continue parking area. wet area water proofing1st floor to 5th floor. Marking for Ac.
B7 Tower G+4P+24th Floor completed Concrete work finish up to 24th slab (all slab work finish just pending for cast the concrete block work finish up to floor 22nd typical. plaster work finish up to floor 15th typical.
B8 Tower G+4P+25th Floor + Terrace Floor & Health Club Completed. (100% Structure Completed) concrete work finish up to floor 21 typical. plaster work finish up to floor 10th typical..
B9 Tower G + 4P+25 Floor + Terrace floor & Health Club Completed (100 % Structure Completed). Plasterwork complete,primer paint complete wall tiles-ceramic kitchen and bathroom complete. all M.E.P. and electrical wall conduiting complete. internal wall paint 2nd code complete.
water proofing wet areas for particular unit-bathroom and kitchen complete. floor tiles started 25th floor down and has complete 20th floor. sub frame work for doors and windows complete. drainage fitting for paticular unit complete. sanitary fitting for particular unit-pipe lines complete. Ac ducting for particular unit Celling work for particular unit kitchen cabinet for particular unit final wooden doors for particular unit aluminium work for particular unit Final paint for particular unit
|